09 April 2026

Stage 2 Update (Transit Committee) - 12 March, 2026

This is the second part of my update on Transit Committee on 12 March. The first part can be found here

Staff presented an update on Stage 2 LRT at that meeting. Stage 2 East achieved substantial completion right before the meeting, which is a big step forwards for that project. But the continuing spalling issue will affect the timeline for trial running, if it is not resolved soon, and there seems to be no indication that will occur. 


The only document: 

The Stage 2 update begins at timestamp 3:21:10 of the video, which can be found here


Stage 2 East

Stage 2 East reached substantial completion the week before the meeting. The independent certifier and City have approved the milestone, and thus, Stage 2 East finally exits the official testing phase. Rideau Transit Maintenance has taken over responsibility for the extension, and is conducting familiarisation training on the line. 

Staff reaffirmed that they will hold a technical briefing before trial running commences. They confirmed that this could only take place when the full fleet of 46 trains was in service, which requires a solution or workaround to the spalling problem. 
Slide describing the five steps: 1. testing, commissioning, and Line 1 integration; 2. substantial completion (you are here); 3. trial running; 4. final system preparations; 5. passenger service


Out of the seven major prerequisites for trial running identified by staff, OC Transpo has completed four. The outstanding items are an end to the spalling issue, trial running oversight in place, and a successful completion of pre-trial running. Trial running will last 21 days, with trains running from Tunney's Pasture to Trim; passengers will be required to disembark at Blair station. 


Work will continue on non-critical issues, including the train control software, platform edge cameras, and minor finishings. Meanwhile, landscaping work will be completed this year, and Highway 174 will be resurfaced. 


Of the 38 Stage 2 vehicles, 30 have been accepted; 7 are in production; and 1 is in dynamic testing. Compare that to the status of the vehicles last September in the black-and-white slide below. 
slide showing the above information with no trains in final inspection or awaiting production
Slide from last September showing 3 awaiting production, 4 in production, 3 in dynamic testing, 1 in final inspection, and 27 accepted



Stage 2 West

Staff also presented a photo update of Stage 2 West. 


Construction is "progressing well," and structural work is nearing completion at all stations. The focus of activity has therefore shifted to testing and commissioning elements including elevators, escalators, ticket machines, and faregates. The first occupancy permit on Stage 2 West has been obtained for the bus operator building at Algonquin Station. 

Work on the bus loops is underway and should be complete at the end of the year. 



Testing and commissioning is ongoing at Westboro Station, as well as work on architectural finishes and fare gadgets. At Kichi Zibi Station, the consortium is testing and commissioning electric and vertical circulation components. And on the Kichi Zibi Mikan, westbound traffic remains at one lane, which will be the configuration until Stage 2 West opens, which is required so that curb work can be completed once the extension opens. 
Image showing platform level at Westboro Station, with pylons around the track, no catenary, and incomplete finishings but the structural work complete
Photo of the interior of Kichi Zibi Station with completed wooden/faux-wood ceilings, and work ongoing on the faregates and glass barriers



At Sherbourne and New Orchard Stations, work is progressing on the communication systems and the passenger information screens. There are also waterproofing and backfilling operations at the latter station. 
Photo of Sherbourne Station showing pylons along the track, work installing various finishings, and a seemingly completed structure including the wall of the trench
A drone shot of New Orchard station showing a complete-looking structure, although the interior is undoubtedly still being worked on


Work on the Lincoln Fields bus loop is underway. The shelters are complete and paving will follow this summer. 
A drone shot of Lincoln Fields station showing exterior work, including on the future bus loop
A shot of Lincoln Fields station showing a bus platform, signage, and finishing work


At Queensview Station, the consortium have been working on "mechanical and electrical works and interior finishing." Pinecrest station work includes the bus loop, station plaza, and the ol' testing 'n' commissioning. 
Exterior shot of Queensview station showing a giant station structure
Interior shot of Pinecrest station showing benches, signage, and PIDs but not all finishings - and no pylons trackside


Bayshore station work was described as relatively advanced. Work here continues on communication systems, elevator testing, and installation of faregates and machines. A catenary is also visible in the shot presented to Committee. Testing and commissioning work is ongoing at Moodie Station. 

Shot of Bayshore station showing the catenary, barriers trackside, and completed-looking finishings and signage
Interior shot of Moodie station showing elevators with some work tools (including an extension cord) visible on the floor


Algonquin and Iris stations are in what was described as a "three-way tie" for the station whose works are most advanced (along with Bayshore). At both stations, staff only described the standard testing and commissioning. 
Photo of the interior of the bus terminal (I think) at Algonquin, showing an escalator, faregates wrapped in plastic (LOL), and the entrance to the washrooms. The wood/faux-wood ceiling has been installed and the lights are on
Photo of the interior of Iris station, showing fare machines wrapped in plastic, faregates protected with plywood, information screens turned on, and the ceiling complete and lighting on



Richmond Road's permanent alignment was completed last year between MacEwen Ave. and Allison Ave. Utility work was also completed west of Ancaster Ave. This year, work will focus further east and on Byron, which was closed between Richardson Avenue and Compton Avenue on 30 March and will remain so until Fall for utility work and repaving. Utility work also continues at Sherbourne Station and Cleary Avenue. 


Woodroffe Avenue was also closed on 30 March and will also remain closed until the Fall. Utilities, traffic signals, and roadwork are being coordinated to occur concurrently at that intersection and road segment. 



Staff shared overall progress on Stage 2 West. Milestones include the completion of track installation; the installation of all OCS poles and 65% of the wiring; and installation of all the jet fans and fire line in the Kichi Zibi tunnel, and overhead catenary rail. 
Slide that shows the milestones I listed above as well as an image of overhead rail and the tunnel, with a gap (?) covered by plyboard


Ongoing work includes the installation of the remaining catenary wire from Lincoln Fields to Tunney's Pasture, turning on the electricity (zap!), testing at Moodie and Bayshore stations, occupancy permits (of which there are 25 needed), cable pulling in the tunnels, and the tunnel ventilation systems. 

Work anticipated to begin or continue this spring includes testing the train control systems, various bus loops, and civil work at the 417 interchanges. 
Slide showing the info I listed above, as well as a train testing at Bayshore station on the westbound track. The catenary looks complete and there are barriers and pylons scattered around, including between the tracks.


Track and system installation is projected for completion in Q3, while commissioning and operations-and-maintenance training will both complete in Q1 of next year. Handover to the City will be in Q2 2027, and the opening preparations will be in Q3 2027. Given that delays have always occurred during testing, this may be an optimistic timeline for opening, which may be pushed back to 2028 or 2029. However, staff emphasized that the completion of Stage 2 East frees up crews and effort to accelerate work on Stage 2 West. 
Slide showing the information discussed above

Compare that to the timeline last September, which showed the track and systems installation complete in Q2 2026, commissioning in Q3, training done in Q4, and handover by the end of this year with an opening date likely in Q1 or Q2 2027. Of course, this was proven to be an optimistic timeline - may there be no more delays on Stage 2 West. 
black and white chart showing the information described above




Stage 2 South

Minor outstanding work remains on Stage 2 South, including a bearing condition monitoring system (Line 1 has really made OC Transpo paranoid); landscaping work; the problematic "frog" at Beech Street, noted as an issue last year; and the voice and video recorders in the trains. 

OC Transpo is evaluating unspecified improvements at Limebank Station following an inquiry from Steve Desroches. 

Finances Again

The written report included a budget chart, as usual. There have been no categories spending over $10 million between July 2025 and this January, except in the contingency (which is now $60 million). This draws the unspent budget down from $417 million to $329 million. Small expenses continue to be taken out on the Stage 1 LRT program. 
Chart which says: January 31, 2026 Project Description Authority Actual Expenditures Funds Reserved/ Committed Unspent/Uncommitted Stage 1 Confederation Line Program 2,130,000,000 2,130,000,000 - - Contingency 121,500,000 105,706,620 9,293,380 6,500,000 Total Stage 1 2,251,500,000 2,235,706,620 9,293,380 6,500,000 Stage 2 Confederation Line Extensions DBF Contract 2,680,832,113 2,457,327,730 223,504,383 - Trillium Line Extension DBFM Contract 850,966,493 706,193,294 6,251,208 -  Deferred Equity  (Maintenance Term) - 138,521,990 - - RTG Stage 2 MOU (includes 38 Alstom vehicles) 516,571,423 493,822,604 22,730,037 18,782 City Costs (includes planning, procurement, property acquisitions, City retained scope, and delivery oversight) 645,042,108 533,736,285 17,223,316 94,082,507 Contingency 366,840,000 214,947,177 59,986,765 91,906,059 Total Stage 2 5,060,252,137 4,544,549,080 329,695,709 186,007,348
Chart which says: July 31, 2025 Project Description Authority Actual Expenditures Funds Reserved/ Committed Unspent/Uncommitted Stage 1 Confederation Line Program 2,130,000,000 2,130,000,000 - - Contingency 115,000,000 103,503,262 11,496,738 - Total Stage 1 2,245,000,000 2,233,503,262 11,496,738 - Stage 2 Confederation Line Extensions DBF Contract 2,680,832,113 2,418,112,463 262,719,650 - Trillium Line Extension DBFM Contract 850,966,493 704,562,438 7,882,065 -  Deferred Equity  (Maintenance Term) - 138,521,990 - - RTG Stage 2 MOU (includes 38 Alstom vehicles) 516,184,423 474,381,158 41,803,265 - City Costs (includes planning, procurement, property acquisitions, City retained scope, and delivery oversight) 574,629,108 510,998,098 28,728,241 34,902,769 Contingency 287,640,000 193,039,182 76,691,999 17,908,819 Total Stage 2 4,910,252,137 4,439,615,329 417,825,220 52,811,588



Until next time. 

No comments:

Post a Comment